Minimum Flow System




My friend, In this posting we will discuss about the pump recycle systems. The pump shall be protected from minimum flow, due to the following reasons;
1. Thermal consideration which has effect to the pump efficiency (The efficiency will decrease significantly at low flow)
2. At low flow, Internal recirculation will be occurred
3. Increase load impeller (both axial and radial)
4. liquid containing a large amount of abrasive particles must flow continuously through the pump. at low flow, the particles can circulate inside the pump and erode the impeller.

Discharge Pump System



My friend, how are you today, ? I hope this weekend give us the best of everything ; find some good experiences, new spirit, and (may be) new planning for the better future, etc.
My friends, Let me share a simple material regarding the discharge pump system, but in this posting, I will only focus on centrifugal pump type. 

Reducer Suction Pump System



Generally, the pump inlet nozzle size is smaller than the suction line size. Therefore, usually, the reducer is required on suction pump nozzle. What the appropriate type of reducer should be applied ? Eccentric or Concentric ?

Pump Suction Strainer



For pump protection, inlet line suction pump should be fitted with a strainer. The strainer can be either T or Y type, permanent or only for temporary. For clean fluid service, such as; demineralized water, boiler feed water, etc the temporary strainer can be used..

Suction Pump Block Valve

Block valve shall be provided on suction and discharge line of pump. The block valve is required for isolation purpose during maintenance. In this posting, we will discuss about the block valve on suction pump. The block valve is not required for suction pump where pump maintenance can be performed without isolating the suction side.

The Art of Line Sizing

As process engineer, we have responsibility in determining the pipe size. Both at proposal and project stage, the adequacy of line size shall be reviewed by process team. I am really sure all of us already familiar with line sizing. We know well both the methods and criteria. Here, we will learn together that actually, the understanding of line sizing philosophy is very important. Line sizing is not just about GOOD and NOT GOOD as we can show in the spreadsheet.

LINE LIST – Input data temperature carefully!

All of us already know that line list is one of deliverable documents provided by process engineer. It is our important product document as a process engineer at IKPT. Many important data will be covered in this document.